Timeline for the Floodplain Reconnection and Salmonid Habitat Restoration on Redwood Creek at the Banducci Site project

* indicates the current step in the planning process
Step 1. Internal Scoping/Development of Purpose and Need
Step 2. Project Scoping: May 1, 1006 through May 31, 2006
Step 3. Prepare Environmental Document: Fall-Winter 2006
Step 4. Release of Environmental Assessment for Public Comment: early Spring 2007 *
Step 5. Considering Public Comment
Step 6. Release of Finding of No Significant Impact: Spring 2007
Step 7. Construction Work on Site: August - October 2007
Step 8. Hands-on Volunteer Revegetation: November 2007-March 2008