The following are the planning steps involved for the Wilderness Plan/EIS

* indicates the current step in the planning process
Step 1. Notice of Intent - Public Scoping
Step 2. Define purpose and need/develop preliminary alternatives
Step 3. Public input on preliminary alterantives
Step 4. Refine alternatives
Step 5. Public review of draft plan/environmental document *
Step 6. Analysis of public comment
Step 7. Prepare final plan/decision document
Step 8. Release final plan/decision document to the public