Step 1. Define purpose and need and develop proposed action
Step 2. Conduct internal scoping and identify issues
Step 3. Identify environmental impacts and develop alternatives
Step 4. Refine proposed action and alternatives
Step 5. Prepare Environmental Assessment
Step 6. Public review of Environmental Assessment
Step 7. Analysis of public comments
Step 8. Prepare Finding of No Significant Impact *
Step 9. Release Finding of No Significant Impact to the public