The Climbing and Canyoneering Management Plan Schedule and Planning process is outlined below.

* indicates the current step in the planning process
Step 1. Define purpose and need
Step 2. Conduct external scoping
Step 3. Conducting natural resource assessments and develop alternatives
Step 4. Conduct preliminary alternative scoping
Step 5. Refine alternatives
Step 6. Identify environmental impacts and select preferred alternative
Step 7. Prepare draft plan/environmental document
Step 8. Public review of draft plan/environmental document
Step 9. Analysis of public comment
Step 10. Prepare final plan/decision document
Step 11. Release final plan/decision document to the public *

This site will be continuously updated through out the planning process.