Public review is an important part of Point Reyes National Seashore's planning process. Public input on the environmental assessment (EA) to be prepared for proposed Verizon Communications Facility was solicited from June 20, 2013 to August 7, 2013. A summary of public input received during scoping can be found in the Document List to the left. The EA is being prepared and will be released for public review and comment in 2015.



* indicates the current step in the planning process
Step 1. Ensure the project application is complete.
Step 2. Conduct public scoping.
Step 3. Post a summary of the comments received on the Seashore website.
Step 4. Prepare the Environmental Assessment (EA). *
Step 5. Public Review of the EA.
Step 6. Consideration of Comments Received.
Step 7. Prepare final plan/decision document
Step 8. Release final plan/decision document to the public